|
|
Armstrong
House Project
The
overarching mission of the Pound Ridge Land Conservancy is to
preserve open land in its natural state in the Town of Pound Ridge.
The Armstrong House meshes with and promotes this mission by providing
a residence to a professionally trained land steward with the
aim of bringing expert land stewardship practices of the PRLC
preserves and other protected open space in Pound Ridge. These
stewardship capabilities will supplement the volunteer efforts
currently existing in the organization.
In
addition, this project will demonstrate how an existing, historical
structure can be preserved while introducing a successful program
of alternative technologies to "power" an off-the-grid
residence.
|
.jpg)
photo
by Carol Cioppa
2008
|
May/June
- Our
June 8th community open house was a success with over
60 folks in attendance. Several high school students
from both Fox Lane and John Jay's AP Environmental classes
presented their research on several research topics
integral to the Armstrong House 'green' projects including
bio-gas opportunities, gray-water recycling, invasives
management and best trail maintenance practices, and,
harnessing the wind at the site through several proposed
devices. House tours and construction updates were given
to many who attended.
- Interior
and exterior framing throughout the house to stabilize
the structure has been substantially completed. This
has involved the reinforcement of the houses walls,
floor and roof.
- Our
trail-head outhouse framing is complete and siding is
nearly completed with a door installed replete with
moon window. Roofing will be done and a small window
installed in the upcoming weeks.
- The
well as been located and tested and has been determined
to be functional at least for the time being.
- Our
solar contract has been negotiated and signed for both
the solar electrical array and domestic solar hot water
panels which are to be mounted on the house roof. Installation
of both solar systems are projected to occur beginning
the end of July. Design plans have been drawn for the
electric solar panel mounting system by our project
engineer, Marchetti Engineering, with volunteer construction
to be commenced over the next several weeks and into
July.
- Our
insulation contract has been nearly finalized and includes
installation of a combination of closed and open cell
bio-based, non-toxic insulation. Spray foam will insulate
the house and create a well-insulated structure in full
compliance with energy codes. As soon as the house in
insulated- we plan to begin installing the exterior
siding early fall.
- The
back-up propane-fired heating system design is nearly
completed with our HVAC contractor.
- Pound
Ridges own master electrician, Charlie George,
supported by a team of volunteers has completed wiring
for the smoke and fire alarm systems and has nearly
completed the rough wiring for the upstairs. Downstairs
rough wiring is anticipated to be completed over the
next several weeks.
- Scraping,
sanding, priming as well as the re-glazing of downstairs
windows continue.
Next on the agenda and into the fall is to get on board
with a plumbing contractor to complete installation of
any needed rough plumbing.
Photo
Gallery 6-30-2008
|
|
March/April
- Structural
stabilization of flooring and floor joists complete.
- Second
floor stabilizing framing underway with front second
floor ceiling joists supported and refitted. Front scaffolding
will be moved to rear of the house to continue structural
re-framing of the second floor
- Interior
demolition of majority of fixtures and old electrical
wiring completed including removal of boiler and all
steel duct-work throughout the structure and garage
-
Meetings with project electrician, Pound Ridge's own
Charlie George and identified solar and mechanical contractors
underway to confirm project's energy systems and installation.
- Research
continues to confirm use of 'green' cell foam insulation
both for vapor barrier and exterior walls and ceiling.
Alternatives identified.
- Framing
of trail-head composting toilet continues with roof
ready for underlayment prior to shingling. Front door
constructed off-site replete with half moon window.
- Majority
of re-claimed lumber has been de-nailed and prepared
for use.
- Continued
project clean-up including winter leaf and fallen tree
removal.
Also-
volunteer hours through the end of March top a total of
375 since the end of August, 2007. Each Saturday, a team
of between 6-16 volunteers including high school students
and community residents, both PRLC board and off-board
volunteers, combine their efforts to move the project
along under the faithful direction and input of our general
contractor Ian Ashby and his crew from South Salem. Contractors,
material suppliers and professional experts continue to
jump on board the project to lend a hand.
Photo
Gallery 3-31-08
|
January/February
- At
the beginning of the year, volunteer hours, including
both high school students seeking community service
credits and community residents, top 200 hours.
- Scaffolding
built to address 2nd floor structural repairs. First
floor foundation and structural stabilization continues
.
- Side
walls and roof construction of composting toilet continues....
- Wood
burning stove assembled and stove piping purchased
and installed to provide temporary heat for indoor
winter construction.
More
developments to be posted soon...
Photo
Gallery 1-31-08
Pre-2008
Work Schedule
|
Benefactors/Participants
to-date
Armstrong
House
Project Blog!
PRLC
Calendar
(updated
regularly to include work session schedule)
Armstrong
House History
1912-The
Armstong House was built as a 3-season retreat at a time when
Pound Ridge was known for its artist community. It is located
on Route 121 near the Ward
Pound Ridge Reservation and overlooks the Cross River Reservoir.
Full
Story
Photo
Gallery Pre-1912
|
|
|