Armstrong House Project

Armstrong House Project

The overarching mission of the Pound Ridge Land Conservancy is to preserve open land in its natural state in the Town of Pound Ridge.

The Armstrong House meshes with and promotes this mission by providing a residence to a professionally trained land steward with the aim of bringing expert land stewardship practices of the PRLC preserves and other protected open space in Pound Ridge. These stewardship capabilities will supplement the volunteer efforts currently existing in the organization.

In addition, this project will demonstrate how an existing, historical structure can be preserved while introducing a successful program of alternative technologies to "power" an off-the-grid residence.


photo by Carol Cioppa

2008

May/June

  • Our June 8th community open house was a success with over 60 folks in attendance. Several high school students from both Fox Lane and John Jay's AP Environmental classes presented their research on several research topics integral to the Armstrong House 'green' projects including bio-gas opportunities, gray-water recycling, invasives management and best trail maintenance practices, and, harnessing the wind at the site through several proposed devices. House tours and construction updates were given to many who attended.
  • Interior and exterior framing throughout the house to stabilize the structure has been substantially completed. This has involved the reinforcement of the house’s walls, floor and roof.
  • Our trail-head outhouse framing is complete and siding is nearly completed with a door installed replete with moon window. Roofing will be done and a small window installed in the upcoming weeks.
  • The well as been located and tested and has been determined to be functional at least for the time being.
  • Our solar contract has been negotiated and signed for both the solar electrical array and domestic solar hot water panels which are to be mounted on the house roof. Installation of both solar systems are projected to occur beginning the end of July. Design plans have been drawn for the electric solar panel mounting system by our project engineer, Marchetti Engineering, with volunteer construction to be commenced over the next several weeks and into July.
  • Our insulation contract has been nearly finalized and includes installation of a combination of closed and open cell bio-based, non-toxic insulation. Spray foam will insulate the house and create a well-insulated structure in full compliance with energy codes. As soon as the house in insulated- we plan to begin installing the exterior siding early fall.
  • The back-up propane-fired heating system design is nearly completed with our HVAC contractor.
  • Pound Ridge’s own master electrician, Charlie George, supported by a team of volunteers has completed wiring for the smoke and fire alarm systems and has nearly completed the rough wiring for the upstairs. Downstairs rough wiring is anticipated to be completed over the next several weeks.
  • Scraping, sanding, priming as well as the re-glazing of downstairs windows continue.

Next on the agenda and into the fall is to get on board with a plumbing contractor to complete installation of any needed rough plumbing.

Photo Gallery 6-30-2008

March/April

  • Structural stabilization of flooring and floor joists complete.
  • Second floor stabilizing framing underway with front second floor ceiling joists supported and refitted. Front scaffolding will be moved to rear of the house to continue structural re-framing of the second floor
  • Interior demolition of majority of fixtures and old electrical wiring completed including removal of boiler and all steel duct-work throughout the structure and garage
  • Meetings with project electrician, Pound Ridge's own Charlie George and identified solar and mechanical contractors underway to confirm project's energy systems and installation.
  • Research continues to confirm use of 'green' cell foam insulation both for vapor barrier and exterior walls and ceiling. Alternatives identified.
  • Framing of trail-head composting toilet continues with roof ready for underlayment prior to shingling. Front door constructed off-site replete with half moon window.
  • Majority of re-claimed lumber has been de-nailed and prepared for use.
  • Continued project clean-up including winter leaf and fallen tree removal.

Also- volunteer hours through the end of March top a total of 375 since the end of August, 2007. Each Saturday, a team of between 6-16 volunteers including high school students and community residents, both PRLC board and off-board volunteers, combine their efforts to move the project along under the faithful direction and input of our general contractor Ian Ashby and his crew from South Salem. Contractors, material suppliers and professional experts continue to jump on board the project to lend a hand.

Photo Gallery 3-31-08

January/February

  • At the beginning of the year, volunteer hours, including both high school students seeking community service credits and community residents, top 200 hours.
  • Scaffolding built to address 2nd floor structural repairs. First floor foundation and structural stabilization continues….
  • Side walls and roof construction of composting toilet continues....
  • Wood burning stove assembled and stove piping purchased and installed to provide temporary heat for indoor winter construction.

More developments to be posted soon...

Photo Gallery 1-31-08

Pre-2008 Work Schedule


Benefactors/Participants to-date

Armstrong House
Project Blog!


PRLC Calendar
(updated regularly to include work session schedule)


Armstrong House History

1912-The Armstong House was built as a 3-season retreat at a time when Pound Ridge was known for its artist community. It is located on Route 121 near the Ward
Pound Ridge Reservation and overlooks the Cross River Reservoir.

Full Story

Photo Gallery Pre-1912